Hurld Park Was Designed for August. Its Playground May Open Before Winter.

November 12, 2026

Off Bedford Road in West Woburn, near the Burlington line, a park designed to keep kids cool is approaching winter as a new playground at the front of an active construction site. In a social media message, Woburn Recreation officials said they were "on track for a possible soft playground opening in just two-to-three weeks," and that they would post a date on the city website and social media, according to the Daily Times Chronicle.

The timing is a little ironic. The city's own plans describe the first phase of Hurld Park as a "heat-resilient" gathering space. Whatever opens this season is the cold-weather edge of a project built for summer, and most of what sets the 11.6-acre site apart is scheduled for 2027 and later.

A park designed around the hottest weeks of the year

On the Hurld Park Vision page, the city says Phase 1 is a southern park that offers "a cool, community gathering space, playground, and splash pad that will keep residents cool as our summers heat up." The design priorities written beside that line include heat resilience and nature-based stormwater management, plus a space accessible to people of all ages and abilities.

The construction documents back up that summer focus. The Phase 1 project manual lists the splash pad equipment by name: a push-button activator, a water jelly, a geyser, misting features, a sparkle, a jet stream and a glomist. The stamped site plan also marks small and large mist towers. The wider design adds a pavilion, a shade canopy, heat-misting stations, a lawn, benches, picnic tables, bike racks, educational signs and nature paths.

You won't need most of that in December. The playground, though, works in any season.

What the playground holds

The city's Phase 1 plans and project manual specify the play area in detail. The Kompan and Earthscapes equipment, along with the surrounding features, includes:

  • An accessible merry-go-round, which the project manual lists as a Kompan universal carousel
  • An accessible double tower for ages 5 to 12, with a double slide, plus a separate Earthscapes double tower and stepper cluster
  • A swing frame with a rope climber, plus a toddler swing
  • A play hut, a spring board and play panels for younger children
  • A boulder scramble and stepping stones
  • Poured-in-place rubber safety surfacing under the play area
  • A drinking fountain with a bottle filler and cafe tables nearby

The accessible carousel and tower come straight from the first design priority. They are also the reason the Daily Times Chronicle has described the park as having a new ADA-accessible playground.

Why the Bedford Road end comes first

The order of construction follows the land. Cummings Brook cuts across the old Hurld School property and feeds a cluster of wetlands on the northern half. That brook and those wetlands are why the city judged the site unsuitable for a new school building years ago. They also explain the layout. The Phase 1 concept puts the playground, the splash pad and the parking lot along the Bedford Road frontage. The wooded area, with trails and boardwalks crossing the brook toward Sheridan Street, belongs to the later passive and restoration phases.

The city plans three bands from south to north. Phase 1 is the playground and splash pad area. Phase 2 is a native meadow and open space with walking paths and benches. Phase 3 is a constructed wetland with stream restoration and its own path system.

Some of the Bedford Road work is already underground. A January 2026 public meeting presentation says the school demolition was completed in August 2025 and that subsurface chambers were installed beneath the future parking lot.

Any soft opening this season will be limited to that front section. The Recreation Department put it plainly in the message the Daily Times Chronicle quoted:

"This will still be an active construction site, so safety is our top priority when thinking about opening the site."

The construction contract also requires the contractor to keep the public out of the work area while building continues.

The calendar, as planned and as it stands

Mayor Michael Concannon and Ward 3 Councilor Jeffrey Dillon had hoped to open the playground over the summer of 2026. The planning documents show how the target moved later and what comes next.

Milestone Planned date Source
Belko Landscaping selected as site contractor December 2025 January 2026 presentation
Groundbreaking on site January 2026 January 2026 presentation
Playground equipment installation begins Spring 2026 January 2026 presentation
Interim playground deadline in contract June 1, 2026 Phase 1 project manual
Playground substantially complete June 2026 January 2026 presentation
Public-use readiness in contract September 1, 2026 Phase 1 project manual
Playground open to the public Late summer/fall 2026 January 2026 presentation
Open space construction Fall 2026 to June 2027 January 2026 presentation
Contract completion May 1, 2027 Phase 1 project manual
Phase 1 park complete; ribbon cutting June 2027; summer 2027 January 2026 presentation
Stream bank and wetland phase begins 2028 Daily Times Chronicle

Both 2026 contract dates in the table are now past targets, and the latest Recreation update still described the playground opening as possible. The playground was meant to arrive in time for one summer of use before the open space work started. If the soft opening goes ahead now, the playground and the splash pad's first real season will both land in summer 2027. Paths through the meadow are on the open space schedule that runs through June 2027, and the brookside wetland work starts after that.

Why it's being built in pieces

The phases also track how the park was paid for, one grant at a time since 2021, on a site first set aside for recreation nearly a decade ago. The Daily Times Chronicle traced the history. Former Mayor Scott Galvin turned the old school property over to the Recreation Commission. In exchange, the city used part of a 4.2-acre parcel off Lowell Street to build the new $35 million Hurld-Wyman Elementary School, which opened on the old Spence Farm parcel in fall 2018.

The city said little more about the site until spring 2021. That year, Galvin and Dillon toured it with abutters and presented a plan. The 28,000-square-foot school, built in 1957, would come down. A playground would go in at the front, and the land across Cummings Brook would become conservation space with walking trails and boardwalks.

The funding then arrived in installments:

  1. A $500,000 Municipal Vulnerability Preparedness grant to advance the design, with the Mystic River Watershed Association as the city's planning partner
  2. $262,500 in federal funding secured by U.S. Rep. Katherine Clark in 2022, followed by a $300,000 state earmark from State Rep. Richard Haggerty
  3. A $500,000 state PARC grant for construction, announced in October 2024
  4. A FY2026 MVP award of $2,451,500, which the Mystic River Watershed Association listed among its partner communities' grants

Belko Landscaping broke ground late last winter on what the Daily Times Chronicle describes as a $3 million park. Dillon has spent much of his City Council tenure pushing for it.

What to expect around Bedford Road this winter

For families nearby, here is what to expect between now and spring. The Recreation Department will post any soft-opening date on the city website and its social media. The playground equipment listed above sits at the Bedford Road end. Construction fencing and crews will stay on the rest of the site. The splash pad, pavilion and misting features belong to the Phase 1 build that the city's schedule finishes by June 2027. The January 2026 presentation puts the ribbon cutting in summer 2027, and the stream bank and wetland restoration along Cummings Brook is forecast to begin in 2028.

Projects that open in stages like this change what a West Woburn street near the Burlington line looks like from one year to the next. If you own near Bedford Road or Sheridan Street and want to talk about how the finished park may affect your plans, Vahan Sardaryan is happy to go through the timeline with you. Schedule a free consultation.